Roadway Improvement Projects
Construction contract was awarded to Grayson Carter in January 2024 with construction anticipated to start in April 2024. Project is anticipated to take six months to complete depending upon weather and utility conflicts.Updated April 11, 2024
Rogers Group was awarded the construction contract in December 2023. Work is anticipated to begin in January 2024 and take approximately nine months to complete, depending upon weather and utility conflicts.Updated Jan. 3, 2024
The project is anticipated to start construction in January 2024 and will take approximately three months to complete.Updated Jan. 3, 2024
Design is complete, though awaiting permitting by the U.S. Army Corps of Engineers before work begins. Construction is anticipated to start mid-2025.Updated April 11, 2024
A corridor study is now underway. Design is anticipated to start in 2024.
Updated Jan. 3, 2024
Currently in the corridor study phase. A public involvement meeting was held in August 2022. Design is anticipated to start in 2024.Updated Jan. 3, 2024
The road is open to traffic. Crews are completing punch list items.
Updated Jan. 2, 2024
Plans are complete, and the City is currently working on right-of-way acquisition for the remainder of properties needed.Updated July 20, 2023
Environmental studies and site assessments are continuing. Public Involvement meeting is anticipated for early 2024.Updated July 20, 2023
All phases of the road are open to traffic. Crews are completing punch list items.
Updated Jan. 2, 2024