Old Gurley Road Improvements
Published on January 3, 2024
SUMMARY
Improvements along Old Gurley Road consisting of approximately 2,550 lane feet and approximately 1,600 lane feet of Mountain Vista Way, just east of Moores Mill Road, to minimize congestion in the area. Work consists of intersection and road modifications to include curb and gutter, drainage and utilities to improve safety and access in the area.
STATUS
Rogers Group was awarded the construction contract in December 2023. Work is anticipated to begin in January 2024 and take approximately nine months to complete, depending upon weather and utility conflicts.
Updated Sept. 27, 2024
COST & FUNDING
Total Cost: $4 million (estimated)
Contractor: Rogers Group