Roadwork Updates
Status reports on the City of Huntsville’s road improvement projects. This includes Road Alerts on routine resurfacing and traffic light installation and Project Updates on major road construction.
Roadwork Updates
Plans are complete, and the City is currently working on right-of-way acquisition for the remainder of properties needed.Updated July 20, 2023
Rogers Group was awarded the construction contract in December 2023. Work is anticipated to begin in January 2024 and take approximately nine months to complete, depending upon weather and utility conflicts.Updated Jan. 3, 2024
The roadway construction was let by ALDOT in September 2023. The contract will be awarded to the low bidder, Rogers Group Inc. The roadway construction will be performed with a detour route in place for motorists to use Trademark Drive to maintain two-way traffic during construction. Construction will begin in April 2024 and take approximately two years to complete.
Updated March 27, 2024
Construction contract was awarded to Grayson Carter in January 2024 with construction anticipated to start in April 2024. Project is anticipated to take six months to complete depending upon weather and utility conflicts.Updated April 11, 2024
The City of Huntsville awarded a $33,499,758 contract to Wiregrass Construction Company on Nov. 2, 2023, to construct the Northern Bypass. Construction began in mid-November 2023 with an estimated construction time of three years, weather permitting. This will include 1 mile of road improvements along U.S. 231 (Memorial Parkway) to accommodate the new intersection. The site is now being cleared, and construction on two of the four bridge culverts is underway. Utility relocations including gas, water, sewer and electric are also underway. Sitework has begun on the west side of Memorial Parkway, and work will begin along Memorial Parkway around the end of March as weather permits. There will be single lane closures along the Parkway as work progresses.Updated March 22, 2024
The Huntsville Area Metropolitan Planning Organization is the transportation planning agency for Huntsville, Madison County, and the cities and towns of Madison, Owens Cross Roads and Triana.
Weather permitting, Tuesday, June 23 beginning at 3 a.m. through 9 a.m., Holmes Avenue (between Greene Street and Lincoln Street) will be closed for the construction associated with the new parking deck structure at the southeast corner of Holmes Avenue and Greene Street.
Traffic control will be in place to direct motorists around this area. Please use alternate routes to avoid congestion in this area during this time.
For any questions please contact Jim McGuffey at 256-427-5300 for any additional information.
Learn more about active roadwork projects at HuntsvilleAL.gov/RoadworkUpdates .
Weather permitting, Tuesday, June 23 beginning at 3 a.m. through 9 a.m., Holmes Avenue (between Greene Street and Lincoln Street) will be closed for the construction associated with the new parking deck structure at the southeast corner of Holmes Avenue and Greene Street.
Traffic control will be in place to direct motorists around this area. Please use alternate routes to avoid congestion in this area during this time.
For any questions please contact Jim McGuffey at 256-427-5300 for any additional information.
Learn more about active roadwork projects at HuntsvilleAL.gov/RoadworkUpdates .
Weather permitting, Tuesday, June 23 beginning at 3 a.m. through 9 a.m., Holmes Avenue (between Greene Street and Lincoln Street) will be closed for the construction associated with the new parking deck structure at the southeast corner of Holmes Avenue and Greene Street.
Traffic control will be in place to direct motorists around this area. Please use alternate routes to avoid congestion in this area during this time.
For any questions please contact Jim McGuffey at 256-427-5300 for any additional information.
Learn more about active roadwork projects at HuntsvilleAL.gov/RoadworkUpdates .
Weather permitting, Tuesday, June 23 beginning at 3 a.m. through 9 a.m., Holmes Avenue (between Greene Street and Lincoln Street) will be closed for the construction associated with the new parking deck structure at the southeast corner of Holmes Avenue and Greene Street.
Traffic control will be in place to direct motorists around this area. Please use alternate routes to avoid congestion in this area during this time.
For any questions please contact Jim McGuffey at 256-427-5300 for any additional information.
Learn more about active roadwork projects at HuntsvilleAL.gov/RoadworkUpdates .
Weather permitting, Tuesday, June 23 beginning at 3 a.m. through 9 a.m., Holmes Avenue (between Greene Street and Lincoln Street) will be closed for the construction associated with the new parking deck structure at the southeast corner of Holmes Avenue and Greene Street.
Traffic control will be in place to direct motorists around this area. Please use alternate routes to avoid congestion in this area during this time.
For any questions please contact Jim McGuffey at 256-427-5300 for any additional information.
Learn more about active roadwork projects at HuntsvilleAL.gov/RoadworkUpdates .
Weather permitting, Tuesday, June 23 beginning at 3 a.m. through 9 a.m., Holmes Avenue (between Greene Street and Lincoln Street) will be closed for the construction associated with the new parking deck structure at the southeast corner of Holmes Avenue and Greene Street.
Traffic control will be in place to direct motorists around this area. Please use alternate routes to avoid congestion in this area during this time.
For any questions please contact Jim McGuffey at 256-427-5300 for any additional information.
Learn more about active roadwork projects at HuntsvilleAL.gov/RoadworkUpdates .
Weather permitting, Tuesday, June 23 beginning at 3 a.m. through 9 a.m., Holmes Avenue (between Greene Street and Lincoln Street) will be closed for the construction associated with the new parking deck structure at the southeast corner of Holmes Avenue and Greene Street.
Traffic control will be in place to direct motorists around this area. Please use alternate routes to avoid congestion in this area during this time.
For any questions please contact Jim McGuffey at 256-427-5300 for any additional information.
Learn more about active roadwork projects at HuntsvilleAL.gov/RoadworkUpdates .
Weather permitting, Tuesday, June 23 beginning at 3 a.m. through 9 a.m., Holmes Avenue (between Greene Street and Lincoln Street) will be closed for the construction associated with the new parking deck structure at the southeast corner of Holmes Avenue and Greene Street.
Traffic control will be in place to direct motorists around this area. Please use alternate routes to avoid congestion in this area during this time.
For any questions please contact Jim McGuffey at 256-427-5300 for any additional information.
Learn more about active roadwork projects at HuntsvilleAL.gov/RoadworkUpdates .