Roadwork Updates
Status reports on the City of Huntsville’s road improvement projects. This includes Road Alerts on routine resurfacing and traffic light installation and Project Updates on major road construction.
Roadwork Updates
Contractor Rogers Group started work in 2023. The contractor shifted all traffic to the substantially-completed service roads in late 2024 and began construction of the new mainline and overpass at Mastin Lake Road.
The project is anticipated to take more than three years to complete. Motorists should expect delays and drive with caution in the 2-mile work zone.
Updated Feb. 21, 2025
The City and ALDOT are working to secure additional funding as the design proceeds. The project will be constructed in phases, with the first phased being near Providence Main. Right of way acquisition is expected to begin in 2025 with construction anticipated in phases from 2026-2029.Updated Feb. 21, 2025
Preliminary engineering and design are 75% complete. A public involvement meeting was held in January 2022. ALDOT is completing design. ROW is anticipated to begin in 2025 with construction scheduled for 2026.Updated Feb. 21, 2025
Plans are complete, and the City is currently working on right-of-way acquisition for the remainder of properties needed.Updated Feb. 4, 2025
Construction contract was awarded to Grayson Carter and Son Contracting in January 2024, and construction began in April 2024. Drainage installation is complete, and grading and concrete work are approximately 90% complete. Paving and median island construction will begin after the grading is complete. Single lane closures are being utilized during off peak hours while contractors are working. Project is anticipated to be complete by the Spring of 2025 depending upon weather and utility conflicts.Updated Feb. 5, 2025
The Huntsville Area Metropolitan Planning Organization is the transportation planning agency for Huntsville, Madison County, and the cities and towns of Madison, Owens Cross Roads and Triana.
Holmes Avenue NE between Dallas Street NE and Steele Street NE will be closed to through traffic on Friday, Nov. 1, from 8 a.m. to 2 p.m. for sewer line repairs. Drivers should use caution in the area, follow all traffic control signs, and consider alternate routes to minimize delays. Contact the City Water Pollution Control Department at 256-883-3719 for more information.
Learn more about active roadwork projects at HuntsvilleAL.gov/RoadworkUpdates .
Weather permitting, Tuesday, June 23 beginning at 3 a.m. through 9 a.m., Holmes Avenue (between Greene Street and Lincoln Street) will be closed for the construction associated with the new parking deck structure at the southeast corner of Holmes Avenue and Greene Street.
Traffic control will be in place to direct motorists around this area. Please use alternate routes to avoid congestion in this area during this time.
For any questions please contact Jim McGuffey at 256-427-5300 for any additional information.
Learn more about active roadwork projects at HuntsvilleAL.gov/RoadworkUpdates .
Weather permitting, Tuesday, June 23 beginning at 3 a.m. through 9 a.m., Holmes Avenue (between Greene Street and Lincoln Street) will be closed for the construction associated with the new parking deck structure at the southeast corner of Holmes Avenue and Greene Street.
Traffic control will be in place to direct motorists around this area. Please use alternate routes to avoid congestion in this area during this time.
For any questions please contact Jim McGuffey at 256-427-5300 for any additional information.
Learn more about active roadwork projects at HuntsvilleAL.gov/RoadworkUpdates .
Weather permitting, Tuesday, June 23 beginning at 3 a.m. through 9 a.m., Holmes Avenue (between Greene Street and Lincoln Street) will be closed for the construction associated with the new parking deck structure at the southeast corner of Holmes Avenue and Greene Street.
Traffic control will be in place to direct motorists around this area. Please use alternate routes to avoid congestion in this area during this time.
For any questions please contact Jim McGuffey at 256-427-5300 for any additional information.
Learn more about active roadwork projects at HuntsvilleAL.gov/RoadworkUpdates .
Weather permitting, Tuesday, June 23 beginning at 3 a.m. through 9 a.m., Holmes Avenue (between Greene Street and Lincoln Street) will be closed for the construction associated with the new parking deck structure at the southeast corner of Holmes Avenue and Greene Street.
Traffic control will be in place to direct motorists around this area. Please use alternate routes to avoid congestion in this area during this time.
For any questions please contact Jim McGuffey at 256-427-5300 for any additional information.
Learn more about active roadwork projects at HuntsvilleAL.gov/RoadworkUpdates .
Weather permitting, Tuesday, June 23 beginning at 3 a.m. through 9 a.m., Holmes Avenue (between Greene Street and Lincoln Street) will be closed for the construction associated with the new parking deck structure at the southeast corner of Holmes Avenue and Greene Street.
Traffic control will be in place to direct motorists around this area. Please use alternate routes to avoid congestion in this area during this time.
For any questions please contact Jim McGuffey at 256-427-5300 for any additional information.
Learn more about active roadwork projects at HuntsvilleAL.gov/RoadworkUpdates .
Weather permitting, Tuesday, June 23 beginning at 3 a.m. through 9 a.m., Holmes Avenue (between Greene Street and Lincoln Street) will be closed for the construction associated with the new parking deck structure at the southeast corner of Holmes Avenue and Greene Street.
Traffic control will be in place to direct motorists around this area. Please use alternate routes to avoid congestion in this area during this time.
For any questions please contact Jim McGuffey at 256-427-5300 for any additional information.
Learn more about active roadwork projects at HuntsvilleAL.gov/RoadworkUpdates .
Weather permitting, Tuesday, June 23 beginning at 3 a.m. through 9 a.m., Holmes Avenue (between Greene Street and Lincoln Street) will be closed for the construction associated with the new parking deck structure at the southeast corner of Holmes Avenue and Greene Street.
Traffic control will be in place to direct motorists around this area. Please use alternate routes to avoid congestion in this area during this time.
For any questions please contact Jim McGuffey at 256-427-5300 for any additional information.
Learn more about active roadwork projects at HuntsvilleAL.gov/RoadworkUpdates .
Weather permitting, Tuesday, June 23 beginning at 3 a.m. through 9 a.m., Holmes Avenue (between Greene Street and Lincoln Street) will be closed for the construction associated with the new parking deck structure at the southeast corner of Holmes Avenue and Greene Street.
Traffic control will be in place to direct motorists around this area. Please use alternate routes to avoid congestion in this area during this time.
For any questions please contact Jim McGuffey at 256-427-5300 for any additional information.
Learn more about active roadwork projects at HuntsvilleAL.gov/RoadworkUpdates .